Dear Labnetwork,
We are currently in the design development phase of constructing a cleanroom facility. The intention is to have about 40-50% of the cleanroom unused on opening day that is reserved for future tools. Although we have scoped out what future equipment we wish to acquire, they are not finalized.
Our contractors wish to install the gas cabinets (they are included in the project budget) for both the currently scoped and future tools. Because the cabinet configurations are equipment dependent (most will be for RIE and CVD/dep tools), we are trying to decide if it's worth the contractors installing 'generic' cabinets for future tools that we can configure ourselves (install gas monitoring, safety showers, etc).
Do you feel this is a feasible approach and if so, what would you install? Or, would you rather install the cabinets yourselves entirely?
Cheers,
Joe
Joseph Losby, PhD
Manager, qLab Operations
joseph.losby at ucalgary.ca
[cid:128655ad-3c75-4672-a2cf-e2191250e71b]<https://io.ucalgary.ca/quantum-city>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mtl.mit.edu/pipermail/labnetwork/attachments/20250304/964b90f0/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: Outlook-fi2maydu.jpg
Type: image/jpeg
Size: 13901 bytes
Desc: Outlook-fi2maydu.jpg
URL: <https://mtl.mit.edu/pipermail/labnetwork/attachments/20250304/964b90f0/attachment.jpg>
More information about the labnetwork
mailing list